aryagraph.generators.dags.project_plan#
- aryagraph.generators.dags.project_plan() DAG[source]#
Construction of a single-family house in 18 tasks, a classic CPM/PERT example.
Durations are working hours (40 h = one week). Arcs carry
lag, a mandatory wait in hours after the predecessor finishes (concrete curing, drywall mud drying); it is 0 elsewhere.critical_path()and the schedulers read node durations only, so to include a lag, insert it as a task of its own on that arc.